PERT diagrams are used by many administrators to support project progress control, especially projects with large scale and workload. So what specifically is a PERT chart? How to build PERT network diagrams quickly and professionally? Let's find the answer with 1C Vietnam in the article below.
A PERT diagram is a chart that shows the progress of a project. A PERT diagram often includes the following elements: tasks to be performed, costs, and time needed to complete the proposed plan. When using this chart, administrators will determine the necessary resources to replenish promptly as well as anticipate possible risks.
Below is an example of a PERT network diagram in a production project consisting of 7 tasks and the following execution sequence:
Work | Implementation time (days) | Quest series |
A | 3 | Do it now |
B | 5 | Do it now |
C | 3 | Do it now |
D | 8 | Do it after completing task A |
E | 4 | Do it after completing tasks A and B |
F | 7 | Do it after completing task C |
G | 3 | Do it after completing mission F |
From the job data in the table, businesses can draw a PERT diagram as follows:
PERT diagrams are often applied in many different project cases, specifically as follows:
To be able to apply this model effectively in practice, administrators need to understand the 4 main elements in the PERT diagram , including: Events, jobs, reserve time and critical path:
Events are milestones in a PERT diagram , marking the start and end dates of a planned activity. Typically, these events are represented as numbered circles. The event starts when the first circle appears with the number 1 and an arrow pointing outward. The event ends at the last circle and has an inward arrow. Events in between will have both an in arrow and an out arrow.
Jobs in a PERT diagram are operational tasks with scheduled staffing and timing, and once completed, move to the next event. Work is represented as a line between event circles. The time to complete the task will correspond to the length of the ramp.
Reserve time in the PERT chart is also called waiting time. This is a period of time calculated to minimize the risk of impact from delayed work on the overall progress of the project. This factor should be marked on the job supply curves. In case tasks are completed earlier than the waiting time, businesses can mark small dots on the arc.
Critical paths are the limiting paths on the PERT chart. The critical path is a way for managers to control and ensure work progress. The longest critical path will be the line connecting the start point to the end point of the PERT chart. If any element along the path is stalled, it means progress is behind schedule.
There are many ways to draw PERT diagrams such as drawing PERT diagrams online, drawing PERT diagrams in excel or using professional PERT diagram software. No matter which method you use, businesses need to follow these 5 basic steps:
Besides PERT, Gantt is also a project management chart used by many people. For general purposes, these two types of charts are created to help administrators monitor project progress. However, each type has its own differences, suitable for each different type of project. Below is a table that differentiates PERT charts and Gantt charts so businesses can refer to and choose the most suitable method.
Factors | Gantt charts | PERT |
Format | Column chart | Network diagram |
Application | Suitable for small-scale and not too complex projects | Suitable for projects with large scale and investment costs and complex nature |
Salient features | Focus mainly on the time it takes to complete certain tasks | Focus on events, to form relationships between tasks, not just focus on completion time. |
Feature | Easy to do, simple, easy to understand. | Difficult to apply because there are many principles to remember. |
Besides applying PERT charts, businesses can deploy software to manage projects more automatically and effectively. Developed on a modern technology platform, 1C:Document Management Digital Office software is a comprehensive solution that provides the necessary features to fully manage the overall life cycle of a project.
Some outstanding features of 1C:Document Management include:
PERT diagram is an effective tool to help administrators control and monitor project progress. This type of chart is especially suitable for large-scale and complex projects. However, PERT is considered difficult to apply and time-consuming to build due to many principles that need to be remembered. Don't forget to follow other articles on 1C Vietnam's website to update useful information about project management!